How to make the installation and debugging plan of precision automatic stamping production line equipment?
To make the installation and debugging plan of precision automatic stamping production line equipment, it is necessary to coordinate all links with project management thinking, and combine the equipment characteristics and production requirements to build a systematic scheme from the dimensions of time node, personnel division and technical process. The following are specific formulation steps and core contents:
First, preliminary preparation: demand analysis and resource planning
1. Define the project benchmark and objectives.
Technical benchmark:
According to the technical agreement of the contract, determine the key indicators (such as stamping accuracy of ±0.05mm, production efficiency of 200 times per minute) and acceptance criteria (continuous operation for 72 hours without failure);
Disassemble the equipment list (punch, feeder, robot, etc.), and make clear the installation sequence and dependency of each equipment (such as installing the punch first and then installing the feeding system).
Time target:
Set the total construction period (such as 60 days), and reserve 10% buffer time to deal with unexpected situations (such as equipment arrival delay and design change);
Determine milestone nodes (installation completion, single machine debugging, linkage acceptance) to match the factory production plan.